乐博体育平台app

ENGINEERING
Waste heat recovery project of 100t electric furnace in a factory
The waste heat recovery project utilizes a heat pipe steam generator steam storage technology to adapt to the flue gas generated during the production of electric furnace. It has the characteristics of high temperature, high dust content, periodic temperature fluctuation and large temperature fluctuation. The project was 103 t/ EAF smelting furnace, the average time of 45min, hot metal ratio 70%-75%; 330 days calculated by year, furnace output up to 1 million 100 thousand tons per year, per ton of steam per ton of 200kg/t, power generation 33.3KW/t
XML 地图